Standard Restaurant Supply | November 2018

Breslin Builders was selected to provide construction services for the Standard Restaurant Supply remodel at the existing facility at Russell Road and Valley View Boulevard.  While the scope was fairly simple and included some existing office demolition to open up more warehouse space, cut in new openings in the existing CMU walls, as well as build some new walls for their showroom and sales area expansion, we none the less had to work around an existing operating business.  Various methods including dust walls, water misting, and ventilation were used to keep the existing public areas open and safe during the work.

Progress photos below:

breslin

Sobb Avenue Warehouse | November 2018 Panel Progress

The Sobb Avenue Warehouse design-build project is progressing and showing great progress this month.  The concrete tilt-up wall panels have been cured enough to be stood in place.  Bull Concrete stood the panels over a couple of days giving the building its vertical appearance.  Once stood the structural steel and panelized roof framing will begin.

Progress photos are below:

 

Sobb Avenue Warehouse | October 2018 Panel Progress

Most of the concrete tilt-up panels at the Sobb Avenue Warehouse project have been poured and are curing for placement at the site.  Soon the building will start to take shape and the next phase of work can begin, including the steel girders and the panelized roof framing system.

Progress photos below:

Sobb Avenue Warehouse | September 2018 Progress

The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Foundations in areas have been poured.  On-site utility installations have started also.  Grading for the panel casting slabs have been completed.

Progress photos are below:

     

Sobb Avenue Warehouse | August 2018 Progress

After many long months and coordinate efforts between the civil engineer, building, and the County, the final permits have been issued from Clark County Building and Safety.  The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Off-site utility installation for the water line is progressing.

Progress photos are below:

Sobb Avenue Warehouse | July 2018 Progress

Grading work is progressing on the new warehouse project Breslin Builders is providing design-build services for. We are working towards final building department approvals, but we are able to get some initial grading started.  In addition to having to import to the site, we also provided on-site crushing efforts to break down the larger caliche boulders found on-site.

Progress photos are below:

Sobb Avenue Warehouse | June 2018 Progress

Breslin Builders has started the site work for the new 32,000 square footage multi-tenant Sobb Avenue Warehouse project.  Clearing and grubbing is taking place in anticipation of a final civil improvement permit.  Additionally, the site will have rock crushing and caliche removal started.  Progress photos are below:

Sobb Avenue Warehouse progress

Breslin Builders has completed the construction documents and recently submitted the Sobb Avenue Warehouse project to Clark County for approvals. We anticipate an April 2018 start pending final Clark County Building Department and Fire Department approvals.

An updated rendering of the project is below.

Sobb Warehouse – Design-Build Project Starting

Breslin Builders is providing design-build services for a new 32,000 square foot office/warehouse project located in the southwest part of the Las Vegas valley.  Located at the end of Sobb Avenue west of Rainbow Boulevard (between Patrick and Post), the project will be a three tenant building with associated warehouse spaces.

Anticipated to be constructed of tilt-up concrete walls with a hybrid roof framing system (wood and metal), the project will build on the decades of experience Breslin Builders has on this type of project and construction.

In addition to the building, the site will have multiple recessed docks, parking, truck access, and a large trash enclosure.

Initial design work has begun, with our next step to including coordination of the land-use approvals with Clark County.  We anticipate a Fall 2018 delivery.

 

Redwood Warehouse Nearing Completion

The Redwood Warehouse project is nearing completion and gearing up for the owner to install their equipment and fixtures to start working the MME cultivation facility.  Breslin Builders provided design-build services for the project, converting an existing metal building vehicle storage and maintenance facility into a new MME cultivation facility.

Progress photos are below:

Redwood Warehouse Progress 3-18-16 - 4 Redwood Warehouse Progress 3-18-16 - 5 Redwood Warehouse Progress 3-18-16 - 6 Redwood Warehouse Progress 3-18-16 - 7 Redwood Warehouse Progress 3-18-16 - 8 Redwood Warehouse Progress 3-18-16 - 9 Redwood Warehouse Progress 3-18-16 - 1 Redwood Warehouse Progress 3-18-16 - 2 Redwood Warehouse Progress 3-18-16 - 3

Westwood Cultivation Progress

Breslin Builders continues our progress on the Westwood Cultivation MME facility in Las Vegas, Nevada.  This facility is being located within an existing warehouse structure and will have about 25% over the overall space developed in this phase, with future work and phases to be completed after opening and needed NV Energy power feed upgrades are performed.  This is our second MME cultivation project in the works, with others on the “drawing board”.  In addition to the cultivation facility, we are also providing design-build services for a fully separated production facility located at the same location.

Progress photos are below:

Westwood Progress - 14 Westwood Progress - 12 Westwood Progress - 13  Westwood Progress - 8 Westwood Progress - 10 Westwood Progress - 2 Westwood Progress - 3 Westwood Progress - 4 Westwood Progress - 5

 

Redwood Warehouse MME Progress

The mechanical, plumbing, and electrical system rough-in installations are taking shape at the Redwood Warehouse MME project in the southwest part of the Las Vegas valley.  In addition, the interior and exterior CMU working is taking place also.

Progress photos are below:

Redwood Warehouse MME Progress Photos 1-7-16 - 2 Redwood Warehouse MME Progress Photos 1-7-16 - 3 Redwood Warehouse MME Progress Photos 1-7-16 - 4 Redwood Warehouse MME Progress Photos 1-7-16 - 5 Redwood Warehouse MME Progress Photos 1-7-16 - 6 Redwood Warehouse MME Progress Photos 1-7-16 - 7 Redwood Warehouse MME Progress Photos 1-7-16 - 8 Redwood Warehouse MME Progress Photos 1-7-16 - 9 Redwood Warehouse MME Progress Photos 1-7-16 - 10 Redwood Warehouse MME Progress Photos 1-7-16 - 1

 

Redwood Warehouse MME Project Work Starts

The permits for the Redwood Warehouse project have been issued and the work at the site is starting to take shape.  This is one of Breslin Builder’s numerous medical marijuana cultivation facility projects we are current working on.

This project consists of the conversion of an existing 20,000 square foot warehouse into a cultivation facility, with Phase I being constructed now and a future Phase II to finish out the grow rooms as needed.

As with the others, this one is a design-build project we have provided design services for and are now providing construction services on.  This project is set to finish in April 2016.  Progress photos area below:

 

Redwood Warehouse Progress Photos 12-4-15 - 1 Redwood Warehouse Progress Photos 12-4-15 - 2 Redwood Warehouse Progress Photos 12-4-15 - 3 Redwood Warehouse Progress Photos 12-4-15 - 4 Redwood Warehouse Progress Photos 12-4-15 - 5 Redwood Warehouse Progress Photos 12-4-15 - 6

Core3D Centres remodel work in progress

Now that we have the permit in hand, Breslin Builders is actively progressing with the remodeling of Core3D’s new facilities. New restrooms, remodeled offices, added break room, and other upgrades are in process for their new dental lab and equipment. Progress photos on some of the work are below:

Core3D Progress - 1

Core3D Progress - 2

Core3D Progress - 5

Core3D Progress - 6

Core3D Progress - 8

« Older Entries