
The slab has been poured at the Sobb Avenue Warehouse project, making way for the concrete tilt-up panels to be formed.
Progress photos are below:



The slab has been poured at the Sobb Avenue Warehouse project, making way for the concrete tilt-up panels to be formed.
Progress photos are below:


The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Foundations in areas have been poured. On-site utility installations have started also. Grading for the panel casting slabs have been completed.
Progress photos are below:


More work progresses on the All-Storage Inspirada project Breslin Builders is completing on Volunteer Boulevard in Henderson, Nevada.
Progress photos are below:


After many long months and coordinate efforts between the civil engineer, building, and the County, the final permits have been issued from Clark County Building and Safety. The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Off-site utility installation for the water line is progressing.
Progress photos are below:


Grading work is progressing on the new warehouse project Breslin Builders is providing design-build services for. We are working towards final building department approvals, but we are able to get some initial grading started. In addition to having to import to the site, we also provided on-site crushing efforts to break down the larger caliche boulders found on-site.
Progress photos are below:

















Breslin Builders has started the site work for the new 32,000 square footage multi-tenant Sobb Avenue Warehouse project. Clearing and grubbing is taking place in anticipation of a final civil improvement permit. Additionally, the site will have rock crushing and caliche removal started. Progress photos are below:


Breslin Builders has been awarded a new retail shell project for Ten15 Craig Tenaya LLC, part of the Dapper Companies in Las Vegas, Nevada. The new project will be constructed on a pad ready site at 7130 West Craig Road (adjacent to the existing Kneaders). The 3,240 square foot shell space will be set up as two future restaurant tenant spaces. We anticipate a tight schedule of 90-120 days for completion.
Before photos are below:


Progress continues on the All-Storage Inspirada project. The third level is framed, roof insulation and panels are being installed, the manager’s apartment is framed with rough-ins starting, site CMU fencing is starting, and finished mechanical and electrical installations are taking place in the storage areas.
Progress photos are below:


The All-Storage I-15 project site work is progressing including installation of the underground on-site utilities. The building pads are also being prepared.
This marks the second mini-storage project we will be completing for All-Storage, and yet another mini-storage project to add to many others we have completed over the years.
Progress photos below:


Breslin Builders has made further progress on the All-Storage Inspirada mini-storage project in Henderson, Nevada. The second level is framed, decked, and the third level is being prepared for the concrete floor pour. The underground site work has progressed also. Installation of the interior metal wall panels on the second level is in progress. Rough electrical and fire sprinkler piping work continues.
Progress photos are below:


Progress is being made at the All-Storage Inspirada project including second level framing, structural steel work, and continued site work. Progress photos are below.


The St. Rose Coronado project is nearing completion with landscaping and other site work being finalized. The work in the interior main level tenant improvements is also being completed. Progress photos are below:


St. Rose Coronado’s recent progress includes more site work being finalized include the massive effort to pave the entire parking lot, installation of walkway pavers, and other related site work. Interior progress includes installation of the tenant improvements, finalize core/shell lobby and restroom areas, and other related items.


Site work and final grading for the parking lot area is in progress at the St Rose Coronado project we are constructing in Henderson, Nevada. The building exteriors are receiving their final coats of paint and other decorative features also. Interior core/shell improvements, as well as interior tenant improvements, are being worked on also.
Some progress photos from a recent site visit are below:


The new retail center at Cactus and Valley View is progressing with the on-site utility installation work taking place now that the off-site underground utility work is completed. Building permits for the project have been issued also, allowing the vertical construction to starting taking place in early 2016.
Progress photos are below:
