Shadow Hills Student Center Progress | May 2018

The Shadow Hills Student Center is nearing completion.  The interiors are finishing up with flooring, ceilings, millwork, and other finish trims.  The exterior work includes the flat work, landscape preparation, fencing, paving, and other related items.  We anticipate work to be completed in June 2018.

Progress photos are below:

Shadow Hills Student Center Progress | April 2018

Much has progressed over the last month at the Shadow Hills Student Center.  Stucco work is completed, site flat work is being formed, interior painting and gypsum board is being completed, ceiling grid is being stalled, as well as final mechanical, plumbing, and electrical work is being progressed.

Progress photos are below: