Station Plaza Storage | Design-Build July 2023

Breslin Builders is providing design-build services for a new multi-story multi-building storage facility to be constructed on an existing pad at the Station Plaza shopping center, anchored by a Walmart Supercenter. Land-use approvals were recently granted by the City of North Las Vegas Planning Commission. The project will contain 808 storage units of various sizes and across the three different buildings.

Lake Mead Storage | May 2023 Progress

We are getting closer to the finish line on this project. Exterior building finishes are nearing completion. The interiors are making great progress also. The site work is progressing with the concrete flat work being installed in preparation for new pavement.

Progress photos are below:

Lake Mead Storage | January 2023 Progress

Much has taken place since our last update and progress is being made on the metal framing and structure of the facility. The framing of 3rd level of this Henderson, Nevada storage facility is being completed. Mechanical, plumbing, and electrical work is progressing on the 1st and 2nd levels. Hallway systems are being installed on the 1st level.

Progress photos and a video area below:

Lake Mead Storage | June 2022 Progress

We have started another multi-story self-storage facility in the Las Vegas valley. This 3-story single-building project is in Henderson Nevada at the Lake Mead Crossing Shopping Center at Lake Mead Parkway and Water Street.

Earthwork and initial underground utility work is currently progressing. The project is expected to be completed 2nd Quarter 2023.

Progress photos are below:

Airport Self Storage | October 2021

Breslin Builders has been engaged to provide design-build services for a new multi-story self storage facility in the Southwest part of the Las Vegas valley. The project consists of various unit sizes across 130,000 square feet of floor space. The project is designed to take advantage of the location and will cater to both local residents, local businesses, but also the tourist and timeshare market, allowing ease of access from the airport and rental car facility.

Breslin’s in-house design group completed conceptual designs and we will be moving into the entitlement and construction documentation phases next. Construction is slated to start 3rd Quarter 2022.

Renderings of the project are below:

Gilespie Storage | June 2021 Progress

Breslin Builders has started our next self storage project in the Las Vegas valley. This one will be located at Gilespie Street just north of Silverado Ranch Boulevard. Clark County Public Works has issued the grading permit and site work is gearing up to begin. The project will consist of multiple style storage buildings including single story and multi-story buildings, a manager’s unit, along with on and off-site improvements.

This project make the 4th self-storage project we have started over the past couple of years, adding to our list of other storage projects we have completed during our 40+ years in the Las Vegas valley.

Mini-Storage at Revere | Final Photos

Below are some of the final photos taken of the new self-storage project Breslin Builders has recently completed. The project is located at 4280 Revere St. in North Las Vegas. Consisting of three different buildings, one being a climate controlled three-story structure, and the other two are single story unconditioned storage buildings.

Mini-Storage at Horizon | Contract Award

Breslin Builders has been awarded another self-storage facility in the Las Vegas valley. This one is in Henderson, Nevada and located on Horizon Ridge Parkway. The three multi-story structures will provide a new option for self-storage in this part of the valley include a dedicated wine storage facility.

 

The site take advantage of the terrain with two of the structure having walk-out basement style buildings. The project is situated on an infill lot, the last in this area, when has upgraded exteriors and added landscape provide features to integrate into the surround neighborhood.

 

Construction will start in March 2021 and is expected to run 14-15 months before being ready for occupancy.

 

 