Mini-Storage at Horizon | July 2021 Progress

Building 2’s slab is in place, Building 1’s walls are cast, and Building 3’s slab work is progressing! Much has changed since our last post about the Mini-Storage at Horizon project. Tracks for wall framing on Building 2 are being placed. Building 1’s final slab preparation is taking place.

Mini-Storage at Horizon | May 2021 Progress

A lot has changed on the mini-storage project in Henderson, Nevada being constructed for Hugh Horne of HPI. CT Equipment has been able to transform what was once a remaining parcel with a wash, black Henderson rock, and lots of large rocks and boulders into a site that will have three separate self-storage buildings. This project is slated to be completed Summer of 2022.