Lotus of Siam | June 2024 Progress

Breslin Builders’ design-build work at the Lotus of Siam remodel is in full swing. We are continuing our efforts for the remodel of the existing restaurant at the famed Commercial Center on East Sahara. The restaurant remodel will expand and provide an update to the existing location including more dining room seating, an added bar area, an expanded kitchen area, and a new commissary kitchen.

We have completed the underground plumbing needs and are progressing the work above the concrete slab now. Framing is taking place both inside the space, as well as new rooftop mechanical platforms for the new mechanical and kitchen equipment requirements. We have also reframed the failing north exterior wall to provide a new framed wall with matching finishes. Per updated code requirements, the required fire separation wall (shaft wall system used) has been installed to help separate this existing space from the balance of the center.

Progress photos are below:

Lotus of Siam Sahara | September 2023 Progress

Breslin Builders has started the preliminary interior demolition work for the remodel of the existing Lotus of Siam restaurant at the Historic Commercial Center on Sahara Avenue in Las Vegas, Nevada. The design-build restaurant remodel will provide an updated interior, refreshed kitchen remodel, added commissary kitchen, a new lounge area, and other updates to the space. The total build-out will be roughly 11,000 square feet.

This continues the prior minor remodel work we have completed for Lotus of Siam over the years, including the remodel of their current operating location on Flamingo.

Work is expected to be completed in 2024, with a final opening date to be determined.

Winchell’s Pub & Grill Eastern | July 2020 Progress

Breslin Builders is providing refresh and update design-build services for the existing Winchell’s Pub & Grill located at 10620 S. Eastern Ave. in Henderson, NV.  We are refreshing the kitchen area, the bar area, and the dining room areas.  Future improvements will also include an update to the patio area.

Progress photos are below:

Lotus of Siam – Flamingo progress

Breslin Builders is currently working on the remodel of the existing Roy’s at 620 E Flamingo for another location for the Lotus of Siam restaurant.  This location will be in addition to their prior location on East Sahara, which Breslin Builders will be remodeling after this location is completed.

Working with the owners, we are closing in the existing open kitchen with new walls and server doors, updating the bar area with new equipment, new paint, finishes, carpeting, and other similar items throughout.  Additionally, we will be providing a new wine room in the private dining area to house their extensive wine collection.  In addition to the interior remodel work we are also providing some exterior updates and repairs also.

Progress photos are below:

The QUAD at Downtown Grand – Design-Build

Breslin Builders has been contracted to provide design-build services for a new 45,000 square foot entertainment complex consisting of meeting rooms, kitchen, outdoor venue, fitness center, and flexible eSports facility, to be constructed in the ground level of the existing old Binion’s parking garage on the east side of Casino Center between Ogden and Stewart.  This facility will expand the Downtown Grand’s offering and abilities for meeting space, entertainment facilities, as well as a fitness center.  A climbing wall is proposed as part of the outdoor venue.

We are currently finalizing the permit and construction drawings for approval by the City of Las Vegas.  In June the City of Las Vegas Planning Commission cleared the way for the project by approving the needed waivers and special use permits.

Breslin Builders is providing both design and construction services on this project.  The project is slated to open to the public second quarter 2018.