All-Storage Inspirada Progress | March 2018

Breslin Builders has made progress on the All-Storage Inspirada project in Henderson, Nevada.  The third floor framing is progressing, site work and grading is taking place, structural steel is in place, and masonry work is finished.

Progress photos are below:

All-Storage Inspirada Progressing

Breslin Builders has made further progress on the All-Storage Inspirada mini-storage project in Henderson, Nevada.  The second level is framed, decked, and the third level is being prepared for the concrete floor pour.  The underground site work has progressed also.   Installation of the interior metal wall panels on the second level is in progress.  Rough electrical and fire sprinkler piping work continues.

Progress photos are below: