Lake Mead Storage | August 2022 Progress

The slab have been poured on the new self-storage facility we are constructing in Henderson, Nevada. This is a hugh milestone in progressing the project.
Progress photos are below:






The slab have been poured on the new self-storage facility we are constructing in Henderson, Nevada. This is a hugh milestone in progressing the project.
Progress photos are below:
Site work and finishes for the various buildings continues at the storage project.
Progress photos are below:
We have started another multi-story self-storage facility in the Las Vegas valley. This 3-story single-building project is in Henderson Nevada at the Lake Mead Crossing Shopping Center at Lake Mead Parkway and Water Street.
Earthwork and initial underground utility work is currently progressing. The project is expected to be completed 2nd Quarter 2023.
Progress photos are below:
The buildings are in the final stages of being finished and the site work is being progressed towards concrete placement for the drive isles.
Progress photos are below:
All City of Las Vegas Building and Public Works permits are finalized and pulled for our new project being completed for Cherry Development! Underground plumbing work is progressing, as well as excavation for the footings. Site utilities are underway. A lot is starting to happen on this 84-unit, 4-story apartment project in downtown Las Vegas, Nevada, and soon things will start coming out of the ground.
Permits have been issued! The site grading and pad work has been completed and the main building foundations are being prepared for our first concrete pour on this project.
Building 2’s slab is in place, Building 1’s walls are cast, and Building 3’s slab work is progressing! Much has changed since our last post about the Mini-Storage at Horizon project. Tracks for wall framing on Building 2 are being placed. Building 1’s final slab preparation is taking place.
Breslin Builders has started our next self storage project in the Las Vegas valley. This one will be located at Gilespie Street just north of Silverado Ranch Boulevard. Clark County Public Works has issued the grading permit and site work is gearing up to begin. The project will consist of multiple style storage buildings including single story and multi-story buildings, a manager’s unit, along with on and off-site improvements.
This project make the 4th self-storage project we have started over the past couple of years, adding to our list of other storage projects we have completed during our 40+ years in the Las Vegas valley.
A lot has changed on the mini-storage project in Henderson, Nevada being constructed for Hugh Horne of HPI. CT Equipment has been able to transform what was once a remaining parcel with a wash, black Henderson rock, and lots of large rocks and boulders into a site that will have three separate self-storage buildings. This project is slated to be completed Summer of 2022.
Grading is completed and underground plumbing and site utility work is progressing on the 63 unit mixed-use apartment project Breslin Builders is providing design-build services for. The downtown located project at Casino Center and Colorado is on track for a 2nd quarter completion in 2020.
Progress photos are below:
Site work has begun on the new multi-story mixed used apartment project in downtown Las Vegas, Nevada. The project will have two ground floor retail spaces, enclosed on grade parking, and 3-levels of apartments above the concrete podium consisting of 63 units total. Each unit is designed as a studio apartment containing approximately 480 square feet each. The project also has three community/gathering rooms. Located at the southwest corner of Casino Center Boulevard and Colorado Avenue, the project is anticipated to be completed April/May 2020. Breslin Builders provided design-build services for the project.
Progress photos are below:
Breslin Builders has begun the site work for a new self-storage facility to be located at Eastern and Horizon Ridge in Henderson, Nevada. The initial work includes deep over excavations of the existing soils in preparation for final grading and building pads. The multi-level self-storage facility, along with the ample covered exterior RV and boat parking area, is anticipated to be completed in 2nd quarter 2020.
Progress photos are below:
Concrete work at the design-build Sobb Avenue Warehouse project is progressing. The slab has been placed and the title-up panels are being formed. Reinforcing and embeds are being placed in each panel also.
Progress photos are below:
The slab has been poured at the Sobb Avenue Warehouse project, making way for the concrete tilt-up panels to be formed.
Progress photos are below:
The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Foundations in areas have been poured. On-site utility installations have started also. Grading for the panel casting slabs have been completed.
Progress photos are below:
More work progresses on the All-Storage Inspirada project Breslin Builders is completing on Volunteer Boulevard in Henderson, Nevada.
Progress photos are below:
After many long months and coordinate efforts between the civil engineer, building, and the County, the final permits have been issued from Clark County Building and Safety. The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Off-site utility installation for the water line is progressing.
Progress photos are below:
Grading work is progressing on the new warehouse project Breslin Builders is providing design-build services for. We are working towards final building department approvals, but we are able to get some initial grading started. In addition to having to import to the site, we also provided on-site crushing efforts to break down the larger caliche boulders found on-site.
Progress photos are below:
Breslin Builders has started the site work for the new 32,000 square footage multi-tenant Sobb Avenue Warehouse project. Clearing and grubbing is taking place in anticipation of a final civil improvement permit. Additionally, the site will have rock crushing and caliche removal started. Progress photos are below:
Site work and final grading for the parking lot area is in progress at the St Rose Coronado project we are constructing in Henderson, Nevada. The building exteriors are receiving their final coats of paint and other decorative features also. Interior core/shell improvements, as well as interior tenant improvements, are being worked on also.
Some progress photos from a recent site visit are below: