Jackpot Joanie’s HS | March 2021 Progress

The tenant improvement work for a new Jackpot Joanie’s at Hualapai and Sunset is progress into the finishes mode.  Ceiling grid, paint, FRP, and other items are being installed in this new location for Jackpot Joanie’s.

 

As with two prior Jackpot Joanie’s locations, Breslin Builders is providing full design-build services on this project also including in-house design and full general contracting services.

 

The project is anticipated to be finished in May | June 2021.

 

Progress photos are below:

Lotus of Siam – Flamingo progress

Breslin Builders is currently working on the remodel of the existing Roy’s at 620 E Flamingo for another location for the Lotus of Siam restaurant.  This location will be in addition to their prior location on East Sahara, which Breslin Builders will be remodeling after this location is completed.

Working with the owners, we are closing in the existing open kitchen with new walls and server doors, updating the bar area with new equipment, new paint, finishes, carpeting, and other similar items throughout.  Additionally, we will be providing a new wine room in the private dining area to house their extensive wine collection.  In addition to the interior remodel work we are also providing some exterior updates and repairs also.

Progress photos are below:

St Rose Coronado – Site Work Progressing

Site work and final grading for the parking lot area is in progress at the St Rose Coronado project we are constructing in Henderson, Nevada.  The building exteriors are receiving their final coats of paint and other decorative features also.  Interior core/shell improvements, as well as interior tenant improvements, are being worked on also.

Some progress photos from a recent site visit are below: