All-Storage Inspirada | April 2018 Progress

Progress continues on the All-Storage Inspirada project.  The third level is framed, roof insulation and panels are being installed, the manager’s apartment is framed with rough-ins starting, site CMU fencing is starting, and finished mechanical and electrical installations are taking place in the storage areas.

Progress photos are below:

All-Storage Inspirada Progressing

Breslin Builders has made further progress on the All-Storage Inspirada mini-storage project in Henderson, Nevada.  The second level is framed, decked, and the third level is being prepared for the concrete floor pour.  The underground site work has progressed also.   Installation of the interior metal wall panels on the second level is in progress.  Rough electrical and fire sprinkler piping work continues.

Progress photos are below: