LA Laser TI | July 2024 Progress

Breslin Builders is in the final stretch of this interior build-out for LA Laser Hair Removal‘s newest location on Blue Diamond Highway. This project is a remodel of a former shoe store and is creating various treatment rooms for their laser hair removal services.

Breslin Builders provided design-build services for this project. The project is anticipated to be completed in July 2024.

Jackpot Joanie’s EF | July 2024 Progress

Demo work has begun on the newest Jackpot Joanie’s location, formally the Magoo’s on East Flamingo. This project continues our relationship with ECL Gaming to add a new Jackpot Joanie’s location to the mix. Like other projects we have completed since 2019 for ECL Gaming, Breslin Builders is providing design-build services for this project also.

The project involves a complete remodel of the interior space including new restrooms, gaming area, seating area, kitchen area, and other support spaces. The project is scheduled for completion by October 2024.

Progress photos are below:

    

Dewey Parking Lot (Raiders)| June 2024 Progress

Breslin Builders is continuing our relationship and work for the Las Vegas Stadium Events Company (Las Vegas Raiders) and furthering development work around Allegiant Stadium. Our current progress includes off-site improvements along Dewey Drive and Polaris Avenue. The work includes half-street improvements, curb and gutter installation, and sidewalks along the two street frontages.

We previously completed parking lot development along Dewey Drive before the 2023-2024 NFL Season. This new work will continue work in this area before the upcoming football season.

Progress photos of the improvements to date:

Lotus of Siam | June 2024 Progress

Breslin Builders’ design-build work at the Lotus of Siam remodel is in full swing. We are continuing our efforts for the remodel of the existing restaurant at the famed Commercial Center on East Sahara. The restaurant remodel will expand and provide an update to the existing location including more dining room seating, an added bar area, an expanded kitchen area, and a new commissary kitchen.

We have completed the underground plumbing needs and are progressing the work above the concrete slab now. Framing is taking place both inside the space, as well as new rooftop mechanical platforms for the new mechanical and kitchen equipment requirements. We have also reframed the failing north exterior wall to provide a new framed wall with matching finishes. Per updated code requirements, the required fire separation wall (shaft wall system used) has been installed to help separate this existing space from the balance of the center.

Progress photos are below:

Lotus of Siam Sahara | May 2024 Progress

Work for the Lotus of Siam restaurant remodel is in full swing now with concrete and steel work progressing. The underground work has been completed and the new wall framing will be starting. The roof penetrations for the new roof top mechanical platforms have been completed with the steel support columns installed.

This continues the prior minor remodel work we have completed for Lotus of Siam over the years, including the remodel of their current operating location on Flamingo.

Work is expected to be completed in 2024, with a final opening date to be determined.

Polaris Care Center | February 2024 Progress

At the February 20th Planning Commission Meeting, Breslin Builders, working with the owner’s representative, secured land-use entitlement approvals for the new congregate care center to be constructed at Polaris and Eldorado in Clark County, Nevada. With these approvals, we can now progress to the construction documentation and engineering phases of the project. Stay tuned for more progress throughout 2024.

Polaris Care Center | November 2023 Progress

Breslin Builders is providing design-build services for a new congregate care facility in the southwest part of the Las Vegas valley. We have completed the initial land-use package for the needed land-use entitlements for the project.

The facility will be located approximately 2.5 acres and will have 76 available beds at this single-story facility. The project is designed with a residential feel to be compatible with the existing neighbors. A mix of painted stucco, concrete tile, and decorative CMU block are proposed for the project, as well as enhanced landscaping around the building.

The project is anticipated to receive land-use approvals early 2024 with construction potentially starting in Q4 2024 or early 2025 once the final Public Works and Building Department permits are obtained.

Lotus of Siam Sahara | September 2023 Progress

Breslin Builders has started the preliminary interior demolition work for the remodel of the existing Lotus of Siam restaurant at the Historic Commercial Center on Sahara Avenue in Las Vegas, Nevada. The design-build restaurant remodel will provide an updated interior, refreshed kitchen remodel, added commissary kitchen, a new lounge area, and other updates to the space. The total build-out will be roughly 11,000 square feet.

This continues the prior minor remodel work we have completed for Lotus of Siam over the years, including the remodel of their current operating location on Flamingo.

Work is expected to be completed in 2024, with a final opening date to be determined.

Dewey Parking Lot – Allegiant Stadium

As part of the ongoing improvements in the area around Allegiant Stadium, another parking option is being added to the mix. Breslin Builders is providing construction services to clear the existing site in preparation for a new parking lot use.

Progress photos of the work in progress are below:

Carter’s For Kids OSHKOSH | July 2023 Progress

Breslin Builders has been actively working on a tenant improvement remodel of an existing retail space at the Silverado Ranch Plaza at Eastern and Silverado Ranch in Las Vegas, Nevada. The former 4,288 square foot T-Mobile space is being transformed into a Carter’s For Kids and OSHKOSH co-branded location.

Breslin Builder is providing the landlord work for the tenant improvement. Worked started in June 2023 and is nearing completion in August. Dan Stuart Davis, Architect is the architect of record for the project.

Our scope includes selective demolition of the existing space, new restrooms, open retail space, and back-of-house areas ready for the tenant to install the needed sales fixture and other tenant supplied items for the retail store.

Project progression photos are below:

Gipsy Nightclub | June 2023 Progress

Our Gipsy Nightclub project keeps moving along. Interior finishes are being installed, as well as exterior site work is progressing. Breslin Builders is working with the owner on some owner updates and changes to help bring their vision for the space to reality.

Progress photos are below:

Jackpot Joanie’s SL | March 2023 Progress

The building is taking on a whole new look with the exterior stucco and finishes being installed. The interior work is progressing also converting this old-style tavern into a new Jackpot Joanie’s location. The only reminder of the old building is the exposed trusses being used as part of the interior decor.

Progress photos are below.

Jackpot Joanie’s SL | November 2022 Progress

This is a newer remodel project we are well underway with for ECL Gaming. This is a remodel of the existing Irene’s tavern into a new Jackpot Joanie’s. The project involves a complete remodel of the interior and an update and a remodel of the exterior facade. The project includes new exterior framing and stucco, cutting openings in the existing CMU walls, new roofing materials installed, and a full buildout on the interior including new restrooms, a new gaming area and bar, and seating areas.

Progress photos are below: