shareDOWNTOWN Apartments | June 2020 Progress

Much progress has been made on the 63 unit apartment project Breslin Builders has provided design-build services on for Cherry Development.  The project is nearing completion with the site work progressing, unit finishes being installed, and inspections taking place.

 

 

 

 

Progress photos are below:

shareDOWNTOWN Apartments | August 2019 Progress

Grading is completed and underground plumbing and site utility work is progressing on the 63 unit mixed-use apartment project Breslin Builders is providing design-build services for.  The downtown located project at Casino Center and Colorado is on track for a 2nd quarter completion in 2020.

Progress photos are below:

shareDOWNTOWN Apartments | July 2019 Progress

Site work has begun on the new multi-story mixed used apartment project in downtown Las Vegas, Nevada.  The project will have two ground floor retail spaces, enclosed on grade parking, and 3-levels of apartments above the concrete podium consisting of 63 units total.  Each unit is designed as a studio apartment containing approximately 480 square feet each.  The project also has three community/gathering rooms.  Located at the southwest corner of Casino Center Boulevard and Colorado Avenue, the project is anticipated to be completed April/May 2020.  Breslin Builders provided design-build services for the project.

Progress photos are below: