shareDOWNTOWN at 11th | August 2022 Progress

Framing for the various floor levels and units is taking shape. Rough-ins for the plumbing and electrical trades are also progressing. Stairs are being installed to each level also.








Framing for the various floor levels and units is taking shape. Rough-ins for the plumbing and electrical trades are also progressing. Stairs are being installed to each level also.
We have progressed to the podium level of the project and are getting things ready for the elevated slab pour. Inserts and embeds are being placed, slab reinforcement has started, progressing to a slab pour.
The 84-unit apartment project is progressing with the concrete podium columns in place and the garage slab areas being graded. Progress has been made on the perimeter CMU walls leading towards the podium form work and pour.
Progress photos are below:
All City of Las Vegas Building and Public Works permits are finalized and pulled for our new project being completed for Cherry Development! Underground plumbing work is progressing, as well as excavation for the footings. Site utilities are underway. A lot is starting to happen on this 84-unit, 4-story apartment project in downtown Las Vegas, Nevada, and soon things will start coming out of the ground.
Concrete foundation work is progressing on the 63 unit mixed-use apartment project Breslin Builders is providing design-build services for. The downtown located project at Casino Center and Colorado is on track for a 2nd quarter completion in 2020.