shareDOWNTOWN at 11th | March 2023 Progress

We are wrapping up our second shareDOWNTOWN project for Cherry Development. This one is shareDOWNTOWN East Fremont (at 11th and Stewart). The finishing touches on the interiors, site work, and other items are being completed.

More information about shareDOWNTOWN can be found here.

Progress photos are below:

shareDOWNTOWN at 11th | May 2022 Progress

The 84-unit apartment project is progressing with the concrete podium columns in place and the garage slab areas being graded. Progress has been made on the perimeter CMU walls leading towards the podium form work and pour.

Progress photos are below:

shareDOWNTOWN at 11th | March 2022 Progress

All City of Las Vegas Building and Public Works permits are finalized and pulled for our new project being completed for Cherry Development! Underground plumbing work is progressing, as well as excavation for the footings. Site utilities are underway. A lot is starting to happen on this 84-unit, 4-story apartment project in downtown Las Vegas, Nevada, and soon things will start coming out of the ground.

shareDOWNTOWN Apartments | September 2019

Concrete foundation work is progressing on the 63 unit mixed-use apartment project Breslin Builders is providing design-build services for.  The downtown located project at Casino Center and Colorado is on track for a 2nd quarter completion in 2020.

Progress photos are below: