Craig and 95 Retail | May 2018 Progress

The new retail building Breslin Builders is constructing for Dapper Development at Craig and 95 is progressing with the slab in place ready for framing.  The slab has a ribbon strip for the two future retail space underground work.  Progress photos are below:

Craig and 95 Retail Shell | Dapper Development | May 2018

Construction work has begun on the new 3,200+ square foot multi-tenant retail shell space at Dapper Development’s Craig and 95 project.  In preparation for the two restaurant tenants a grease interceptor has been installed, along with the balance of the shell underground plumbing.  Prior to the underground work, grading was completed and concrete forms were in place.  We anticipate the project having an approximate 90 day schedule.

Progress photos are below: