shareDOWNTOWN at 11th | March 2022 Progress

All City of Las Vegas Building and Public Works permits are finalized and pulled for our new project being completed for Cherry Development! Underground plumbing work is progressing, as well as excavation for the footings. Site utilities are underway. A lot is starting to happen on this 84-unit, 4-story apartment project in downtown Las Vegas, Nevada, and soon things will start coming out of the ground.

shareDOWNTOWN at 11th | January 2022 Progress

Our next apartment project in downtown Las Vegas, Nevada has started! This one will be similar to the one we completed at Casino Center and Colorado, with an added floor to increase the unit count to 84 units. The project will progress throughout 2022 with an anticipated completed first part of 2023.

Bali Hai Tiki Bar | November 2021 Progress

Our design-build project at the Bali Hai Golf Course Club House, which is adding a new sports bar within an existing covered patio area, is progress towards the end.

Finishes are being installed including various tiki style materials, creating a fun place for a drink or food after (or before) your 18 holes of golf. Playing off the “tiki” theme, but also keep with the overall Polynesian theme of the club house and golf course, the new sports bar be your next stop in your experience at the Bali Hai Golf Course.

Breslin Builders has provided both design and construction of this newest addition to the clubhouse, which is a project we provided initial design-assist and construction services in the early 2000’s, and have provided various construction services over the past decades at the property.

Airport Self Storage | October 2021

Breslin Builders has been engaged to provide design-build services for a new multi-story self storage facility in the Southwest part of the Las Vegas valley. The project consists of various unit sizes across 130,000 square feet of floor space. The project is designed to take advantage of the location and will cater to both local residents, local businesses, but also the tourist and timeshare market, allowing ease of access from the airport and rental car facility.

Breslin’s in-house design group completed conceptual designs and we will be moving into the entitlement and construction documentation phases next. Construction is slated to start 3rd Quarter 2022.

Renderings of the project are below:

Lucky 7’s at Trop and Jones | September 2021 Progress

We have started the interior remodel work converting an old Irene’s Lounge into a new Lucky 7’s tavern. This project is owned by the same client that we have completed Jackpot Joanie’s for, as well as currently constructing their new corporate offices, Ron Winchell and Eclipse Gaming. Breslin Builders is providing both design and construction services for this project.

The initial phase involved gutting the existing shell space in preparation for the new work. The existing bar, kitchen, restrooms, and other related spaces have been removed to make way for the new tavern use.

Mini-Storage at Horizon | July 2021 Progress

Building 2’s slab is in place, Building 1’s walls are cast, and Building 3’s slab work is progressing! Much has changed since our last post about the Mini-Storage at Horizon project. Tracks for wall framing on Building 2 are being placed. Building 1’s final slab preparation is taking place.

Gilespie Storage | June 2021 Progress

Breslin Builders has started our next self storage project in the Las Vegas valley. This one will be located at Gilespie Street just north of Silverado Ranch Boulevard. Clark County Public Works has issued the grading permit and site work is gearing up to begin. The project will consist of multiple style storage buildings including single story and multi-story buildings, a manager’s unit, along with on and off-site improvements.

This project make the 4th self-storage project we have started over the past couple of years, adding to our list of other storage projects we have completed during our 40+ years in the Las Vegas valley.

Jackpot Joanie’s HS | June 2021 Update

Our latest Jackpot Joanie’s location completed for Eclipse Gaming is complete and opened today! This is our third location we have provided design-build services for Eclipse Gaming and have at least two more locations in progress. Below are photos from their pre-opening to get the place ready for there customers this afternoon. Final photos will follow once we have these ready.

Stop of by and visit their newest location at the end of Sunset and Hualapai, 6420 S. Hualapai Way, Las Vegas, Nevada.

Brew It Coffee at 601 Bridger | May 2021 Progress

Progress is well underway for a new coffee shop in downtown Las Vegas. Breslin Builders provided design-build services for the Brew It Coffee shop at 601 Bridger (corner of 6th Street and Bridger in downtown). The project is a continuation of other work we have completed over the past year including the entire upper level of the building for Schwartz Law‘s new office. We are also completing lobby and restroom upgrades on the main level, as well as creating a space for future tenant improvements on the main level.

Eclipse Gaming Office | May 2021 Progress

Early on a Friday morning, the final slabs were poured at the Eclipse Gaming Office on Buffalo and Teco in the southwest part of the Las Vegas valley. The office area slab and the warehouse areas were completed, ready for the next steps including masonry walls.

Mini-Storage at Horizon | May 2021 Progress

A lot has changed on the mini-storage project in Henderson, Nevada being constructed for Hugh Horne of HPI. CT Equipment has been able to transform what was once a remaining parcel with a wash, black Henderson rock, and lots of large rocks and boulders into a site that will have three separate self-storage buildings. This project is slated to be completed Summer of 2022.