Tag Archives: site work

Huntridge Retail | June 2019 Progress

Breslin Builders, working for Dapper Construction and Dapper Development, has progressed the new two tenant restaurant building out of the ground.  The slab has been poured and the unique CMU walls are being completed.

The building, designed by BunnyFish Studios, has a very unique and custom curvilinear roof, making this a one of a kind structure.  Housing two locally recognized restaurants, Roberto’s Taco Shop and Capriotti’s Sandwich Shop, the space will be a welcomed addition to the existing Huntridge Shopping Center at Charleston Boulevard and Maryland Parkway.

Progress photos are below:

Rainbow Commons | June 2019 Progress

Working continues on the multi-building retail center at Sunset and Rainbow.  The corner c-store, a 7-Eleven, is complete, Building 4 (retail) is framed and rough-ins are being finalized, Building 3 (retail) is being framed with rough-ins started, and Building 5 (two-story office) is being started soon.

Progress photos are below:

Huntridge Retail | May 2019 Progress

Breslin Builders, working for Dapper Construction and Dapper Development, has progressed the new two tenant restaurant building out of the ground.  After a few months of existing utility relocation, site work, and underground installations, we have columns in place ready to put the slab.

The building, designed by BunnyFish Studios, has a very unique and custom curvilinear roof, making this a one of a kind structure.  Housing two locally recognized restaurants, Roberto’s Taco Shop and Capriotti’s Sandwich Shop, the space will be a welcomed addition to the existing Huntridge Shopping Center at Charleston Boulevard and Maryland Parkway.

Progress photos are below:

  

Rainbow Commons | March 2019 Progress

Breslin Builders is making vertical progress on the Rainbow Commons center on Rainbow between Sunset and the 215.  The framing for building 1, a future 7-Eleven c-store is completed.  Foundation work for building 4 is started also.

Progress photos are below:

Sobb Avenue Warehouse | November 2018 Framing Progress

Now that the walls are stood, the roof framing for the Sobb Avenue Warehouse project is well underway for the project.  The structural columns and girders have been placed prior to the roof framing starting.  The exterior of the wall panels are being cleaned up and patched.

Progress photos are below:

Sobb Avenue Warehouse | November 2018 Panel Progress

The Sobb Avenue Warehouse design-build project is progressing and showing great progress this month.  The concrete tilt-up wall panels have been cured enough to be stood in place.  Bull Concrete stood the panels over a couple of days giving the building its vertical appearance.  Once stood the structural steel and panelized roof framing will begin.

Progress photos are below:

 

Sobb Avenue Warehouse | October 2018 Panel Progress

Most of the concrete tilt-up panels at the Sobb Avenue Warehouse project have been poured and are curing for placement at the site.  Soon the building will start to take shape and the next phase of work can begin, including the steel girders and the panelized roof framing system.

Progress photos below:

Sobb Avenue Warehouse | September 2018 Progress

The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Foundations in areas have been poured.  On-site utility installations have started also.  Grading for the panel casting slabs have been completed.

Progress photos are below:

     

Sobb Avenue Warehouse | August 2018 Progress

After many long months and coordinate efforts between the civil engineer, building, and the County, the final permits have been issued from Clark County Building and Safety.  The foundation reinforcing is progressing on the new warehouse project Breslin Builders is providing design-build services for. Off-site utility installation for the water line is progressing.

Progress photos are below:

Sobb Avenue Warehouse | July 2018 Progress

Grading work is progressing on the new warehouse project Breslin Builders is providing design-build services for. We are working towards final building department approvals, but we are able to get some initial grading started.  In addition to having to import to the site, we also provided on-site crushing efforts to break down the larger caliche boulders found on-site.

Progress photos are below:

Sobb Avenue Warehouse | June 2018 Progress

Breslin Builders has started the site work for the new 32,000 square footage multi-tenant Sobb Avenue Warehouse project.  Clearing and grubbing is taking place in anticipation of a final civil improvement permit.  Additionally, the site will have rock crushing and caliche removal started.  Progress photos are below:

Craig and 95 Retail Shell Progress | April 2018

Breslin Builders has been awarded a new retail shell project for Ten15 Craig Tenaya LLC, part of the Dapper Companies in Las Vegas, Nevada.  The new project will be constructed on a pad ready site at 7130 West Craig Road (adjacent to the existing Kneaders).  The 3,240 square foot shell space will be set up as two future restaurant tenant spaces.  We anticipate a tight schedule of 90-120 days for completion.

Before photos are below:

All-Storage Inspirada | April 2018 Progress

Progress continues on the All-Storage Inspirada project.  The third level is framed, roof insulation and panels are being installed, the manager’s apartment is framed with rough-ins starting, site CMU fencing is starting, and finished mechanical and electrical installations are taking place in the storage areas.

Progress photos are below:

« Older Entries