Tag Archives: retail

Craig and 95 Retail | August 2018 Progress

More progress on the Craig and 95 Retail shell building for Dapper Development.  Stucco is completed and primed, CMU planters being finished, decorative steel items have been installed, as well as other items progressing.

Progress photos are below:

Craig and 95 Retail | May 2018 Progress

The new retail building Breslin Builders is constructing for Dapper Development at Craig and 95 is progressing with the slab in place ready for framing.  The slab has a ribbon strip for the two future retail space underground work.  Progress photos are below:

Craig and 95 Retail Shell | Dapper Development | May 2018

Construction work has begun on the new 3,200+ square foot multi-tenant retail shell space at Dapper Development’s Craig and 95 project.  In preparation for the two restaurant tenants a grease interceptor has been installed, along with the balance of the shell underground plumbing.  Prior to the underground work, grading was completed and concrete forms were in place.  We anticipate the project having an approximate 90 day schedule.

Progress photos are below:

St. Rose Coronado Finalizing

Breslin Builders is wrapping up the final items in the St. Rose Coronado project.  Main level tenants have been finalized and tenants are moving into their spaces.  Bike racks are being installed at various areas at the site per City of Henderson requirements.  The landscaping along St. Rose Parkway has also been installed.

Progress photos are below:

St. Rose Coronado Progress

Nearing completion, the St Rose Coronado project is progressing along.  Carports are finished, site landscaping is being finished, interior core areas are being finalized, first floor tenant improvements, with final inspections and other items being completed.  Progress photos are below.

St. Rose Coronado progress

The St. Rose Coronado project is nearing completion with landscaping and other site work being finalized.  The work in the interior main level tenant improvements is also being completed.  Progress photos are below:

St. Rose Coronado progress

St. Rose Coronado’s recent progress includes more site work being finalized include the massive effort to pave the entire parking lot, installation of walkway pavers, and other related site work.  Interior progress includes installation of the tenant improvements, finalize core/shell lobby and restroom areas, and other related items.

St Rose Coronado – Site Work Progressing

Site work and final grading for the parking lot area is in progress at the St Rose Coronado project we are constructing in Henderson, Nevada.  The building exteriors are receiving their final coats of paint and other decorative features also.  Interior core/shell improvements, as well as interior tenant improvements, are being worked on also.

Some progress photos from a recent site visit are below:

Southwest Marketplace Completing

Breslin Builders is putting the finishing touches on the Southwest Marketplace project located at Rainbow and Warm Springs in the southwest Las Vegas valley area.  The project is an expansion of the existing inline retail center, anchored by a Smith’s Food and Drug center.  In addition to the shell building, we have also provided tenant demising and other landlord items for two of the future tenant spaces.

 

 

St. Rose Coronado Center Progressing

Breslin Builders has made a lot progress on the St. Rose Coronado Center over the past few months.  The project is located in Henderson, Nevada on St.Rose Parkway (south of the 215 freeway).  The project consists of a 3-story office building (tilt-up and metal frame construction) and two wood framed in-line retail buildings.

Currently we are finishing up the retail shell spaces, progressing the office shell space, and starting multiple interior office tenant improvement spaces on the main level.  Site work will start soon with a Fall 2017 completion date anticipated.

Southwest Marketplace Progress

Work on the 9,845 square foot retail expansion at the Southwest Marketplace retail center, located at 8050 South Rainbow Avenue in Las Vegas, Nevada, is progressing with framing completed and rough electrical, plumbing, and mechanical installation taking place. The project will expand the existing retail center, anchored by a Smith’s grocery store. The project is anticipated to be completed for tenant occupancy this fall.

Kemp Retail Completed

Breslin Builders has recently completed the Kemp Retail Center on Cactus in southwest part of Las Vegas, Nevada.  The inline retail center includes a free standing restaurant drive-thru pad shell building also.  Other items included as part of the project include full half-street improvements on Cactus, a pump house for the required fire pump (due to low water pressure in the developing area), and full site improvements.

Photos of the completed work are below:

St. Rose Coronado Center Work Progressing

Breslin Builder’s work on the new office and retail center at St. Rose and Coronado in Henderson, Nevada is progressing with underground plumbing and concrete foundations being placed.  The project consists of multiple buildings including a three story tilt-up office building and two single story inline retail buildings, along with a fast food pad.

Progress photos are below:

Kemp Retail Gets Some Color

Our Kemp Retail project on Cactus west of I-15 is getting some final colors on the exterior.  Construction is progressing with curbs and other site amenities being installed also.  Breslin Builders will also be starting phase two later this year once the proper approvals and permits are in place.

Some progress photos are below:

Kemp Retail Progressing

The new retail center on Cactus just west of the I-15 is progressing with the second retail building framed and the first building being wrapped for stucco.  Off site work along Cactus is progressing also including curbs, gutters, sidewalks, and other street improvements.

Progress photos are below:

Kemp Retail 5-6-16 - 17-1200 Kemp Retail 5-6-16 - 15-1200 Kemp Retail 5-6-16 - 13-1200 Kemp Retail 5-6-16 - 14-1200 Kemp Retail 5-6-16 - 12-1200 Kemp Retail 5-6-16 - 11-1200 Kemp Retail 5-6-16 - 10-1200 Kemp Retail 5-6-16 - 8-1200 Kemp Retail 5-6-16 - 7-1200 Kemp Retail 5-6-16 - 6-1200 Kemp Retail 5-6-16 - 4-1200 Kemp Retail 5-6-16 - 2-1200

« Older Entries