Lake Mead Storage | June 2022 Progress

We have started another multi-story self-storage facility in the Las Vegas valley. This 3-story single-building project is in Henderson Nevada at the Lake Mead Crossing Shopping Center at Lake Mead Parkway and Water Street.

Earthwork and initial underground utility work is currently progressing. The project is expected to be completed 2nd Quarter 2023.

Progress photos are below:

shareDOWNTOWN at 11th | May 2022 Progress

The 84-unit apartment project is progressing with the concrete podium columns in place and the garage slab areas being graded. Progress has been made on the perimeter CMU walls leading towards the podium form work and pour.

Progress photos are below:

Lucky 7’s at Trop and Jones | September 2021 Progress

We have started the interior remodel work converting an old Irene’s Lounge into a new Lucky 7’s tavern. This project is owned by the same client that we have completed Jackpot Joanie’s for, as well as currently constructing their new corporate offices, Ron Winchell and Eclipse Gaming. Breslin Builders is providing both design and construction services for this project.

The initial phase involved gutting the existing shell space in preparation for the new work. The existing bar, kitchen, restrooms, and other related spaces have been removed to make way for the new tavern use.

Brew It Coffee at 601 Bridger | May 2021 Progress

Progress is well underway for a new coffee shop in downtown Las Vegas. Breslin Builders provided design-build services for the Brew It Coffee shop at 601 Bridger (corner of 6th Street and Bridger in downtown). The project is a continuation of other work we have completed over the past year including the entire upper level of the building for Schwartz Law‘s new office. We are also completing lobby and restroom upgrades on the main level, as well as creating a space for future tenant improvements on the main level.

Jackpot Joanie’s SE | March 2021 Progress

Our second design-build Jackpot Joanie’s location at Sahara and Eastern is nearing completion.  The old Dream Furniture location has been completely renovated into a new Jackpot Joanie’s location.  Breslin Builders provided full design-build services for this project.

 

Progress photos are below:

Mini-Storage at Horizon | Contract Award

Breslin Builders has been awarded another self-storage facility in the Las Vegas valley. This one is in Henderson, Nevada and located on Horizon Ridge Parkway. The three multi-story structures will provide a new option for self-storage in this part of the valley include a dedicated wine storage facility.

 

The site take advantage of the terrain with two of the structure having walk-out basement style buildings. The project is situated on an infill lot, the last in this area, when has upgraded exteriors and added landscape provide features to integrate into the surround neighborhood.

 

Construction will start in March 2021 and is expected to run 14-15 months before being ready for occupancy.

 

 

theBLOQparq Announcement

Breslin Builders has been selected as part of the development team involved on a new and exciting, as well as unique, project being developed in the City of Henderson, Nevada at the intersection of Boulder Highway and Sunset. Chosen for our experience in similar project types, including our highly successful design-build efforts provided for the Downtown Container Park, and our relationship with Xtreme Cubes, we are ready to lend our insight, design-assist services, and ultimately be the general contractor of record for theBLOQparq project.

 

More information about the project and team can be found on their recently launched website – https://thebloqparq.com

 

We look forward to breaking ground in 2021!

 

Mini-Storage at Revere | July 2020 Progress

Breslin Builders progresses the new self-storage project on Revere Street (south of Craig Road) in North Las Vegas.  The multi-building project, including a large 3-story facility, is slated for completion in September/October 2020.

 

Progress photos are below:

 

Winchell’s Pub & Grill Eastern | July 2020 Progress

Breslin Builders is providing refresh and update design-build services for the existing Winchell’s Pub & Grill located at 10620 S. Eastern Ave. in Henderson, NV.  We are refreshing the kitchen area, the bar area, and the dining room areas.  Future improvements will also include an update to the patio area.

Progress photos are below:

shareDOWNTOWN Apartments | June 2020 Progress

Much progress has been made on the 63 unit apartment project Breslin Builders has provided design-build services on for Cherry Development.  The project is nearing completion with the site work progressing, unit finishes being installed, and inspections taking place.

 

 

 

 

Progress photos are below: