Tag Archives: construction

Lotus of Siam | Flamingo – Open for business

The new Lotus of Siam at 620 E. Flamingo, a remodel that Breslin Builders has recently completed for the restaurant, has opened.  We are excited to provide our design-build services at their new location.

Check out this ReviewJournal.com article about the opening – click here.

In addition to the full remodel work,  we will also be completing an additional climate controlled wine room in the private dining room.  We will also be starting the design and construction services on their previous location at Commercial Center on Sahara Avenue to renovate and restore it for operations again.

Photos of the new space are to follow also.

St. Rose Coronado Progress

Nearing completion, the St Rose Coronado project is progressing along.  Carports are finished, site landscaping is being finished, interior core areas are being finalized, first floor tenant improvements, with final inspections and other items being completed.  Progress photos are below.

All Storage Inspirada Progress

Great progress is being made on the All Storage Inspirada project in Henderson, Nevada.  Two of the building slabs have been placed, masonry is being completed, and framing of the  main level storage units and main office area is being completed.  Progress photos are below.

St. Rose Coronado progress

The St. Rose Coronado project is nearing completion with landscaping and other site work being finalized.  The work in the interior main level tenant improvements is also being completed.  Progress photos are below:

Shadow Hills Student Center started

Work on the next phase of the Shadow Hills Church complex has started with the new Student Center grading started.  Over the next few months a new student center for the church will rise from the ground providing classroom facilities and gathering spaces for the church youth.

This project marks one of many Breslin Builders has completed for the Shadow Hills church, including our initial project of almost two decades ago when the church construction work for the worship building was originally built.

 

All Storage Inspirada – Earthwork Progressing

The laborious task of preparing the site for the foundation systems at the All Storage Inspirada project in Henderson, Nevada is progressing.  The site contains many large rocks that have required heavy equipment to unearth and strategically remove.  Screening and blending are being used to get the most benefit from the on-site soils.

Check out some photos from the site showing the earthwork progression:

Dollar Storage finishing up

The Dollar Storage project Breslin Builders is constructing on Centennial Boulevard in North Las Vegas is nearing completion.  Asphalt paving was recently completed for the project.  Finish work for the various mechanical, electrical, fire sprinkler, painting, and other systems is also being completed.

Progress photos are below:

Southwest Marketplace Completing

Breslin Builders is putting the finishing touches on the Southwest Marketplace project located at Rainbow and Warm Springs in the southwest Las Vegas valley area.  The project is an expansion of the existing inline retail center, anchored by a Smith’s Food and Drug center.  In addition to the shell building, we have also provided tenant demising and other landlord items for two of the future tenant spaces.

 

 

All Storage Inspirada – Coming Soon

Breslin Builders has been awarded the contract to building the newest All Storage facility in the Las Vegas area.  Located on Volunteer Boulevard in close proximity to the Henderson Executive Terminal, this project will transform raw desert into a new multi-building gated storage facility.  We are currently waiting for final building permits to be issued from the City of Henderson and will start construction as soon as the permits are issued.

 

 

Oquendo Center Expansion – Pre-Demo Work

Breslin Builder is getting things in place for the start of the demolition work of the existing office building at the Oquendo Center at the corner of Eastern and Oquendo in Las Vegas, Nevada.  The unused and outdated building, Western Veterinarian Center’s original building prior to their current facility was built, will be demolished to make way for a new two-story 30,000 square foot office building.  The new office space will allow the current space in the current Oquendo Center to be converted to more convention and teaching space.  Demolition is slated by the end of the month with new construction starting in August 2017.

St. Rose Coronado Center Progressing

Breslin Builders has made a lot progress on the St. Rose Coronado Center over the past few months.  The project is located in Henderson, Nevada on St.Rose Parkway (south of the 215 freeway).  The project consists of a 3-story office building (tilt-up and metal frame construction) and two wood framed in-line retail buildings.

Currently we are finishing up the retail shell spaces, progressing the office shell space, and starting multiple interior office tenant improvement spaces on the main level.  Site work will start soon with a Fall 2017 completion date anticipated.

Oquendo Center Expansion Work

Breslin Builders will be providing construction services for Oquendo Center’s (Western Veterinarian Conference) new expansion to add more convention, lecture, and meeting space to their existing facility.  Prior to construction services, we have been working with SH Architecture and the owner providing design-assist pre-construction services.

The first steps in the expansion includes the construction of a new approximately 30,000 square foot office building, which replace their existing unused original office building on the northwest corner of their property (Eastern and Oquendo).  Additionally, we will be constructing a new free standing “barn” to replace the existing one being removed as part of the expansion work.

The new expansion work will require changes to some of the original work we previously completed including the demolition of their existing large animal barn, moving their offices to the new building, site changes, and other adjustments.

Demolition work is slated to start by August 1st with overall work anticipated to be completed by April 2019.  More updates and renderings will follow as the project progresses.

Shadow Hills Student Center Awarded

Building upon the prior work completed at the Shadow Hills Baptist Church facility over the past two decades, Breslin Builders has been awarded the newest project being constructed, that being their new Student Center.

The project is slated to start in the next 30 days and will contain almost 31,000 square feet of various youth classroom spaces, youth worship rooms, and a large multi-purpose room for various functions.

The project is located at the existing Shadow Hills Baptist Church property on Vegas Drive.

SH Architecture is the architect of record on the project.

Dollar Self Storage Work Progressing

Work on the new 657 unit, 88,500+ square foot Dollar Self Storage facility in North Las Vegas is progressing with the framing on the storage units currently in progress. The front office building is being closed in with gypsum board being installed on the inside also.

This is another of the many mini-storage projects Breslin Builders has constructed over the three decades we have been in business. The facility is scheduled to be opened Fall 2017.

 

Southwest Marketplace Progress

Work on the 9,845 square foot retail expansion at the Southwest Marketplace retail center, located at 8050 South Rainbow Avenue in Las Vegas, Nevada, is progressing with framing completed and rough electrical, plumbing, and mechanical installation taking place. The project will expand the existing retail center, anchored by a Smith’s grocery store. The project is anticipated to be completed for tenant occupancy this fall.

Domino’s Pizza TI Progressing

Breslin Builders has started the tenant improvement construction efforts for a new Domino’s Pizza at the existing shopping center at the northeast corner of West Sahara and South Decatur. The space converts two vacant tenant spaces into one Domino’s Pizza establishment. To date demolition work and underground plumbing installations have been completed. Look for this new location to open in Spring 2017.

Kemp Retail Completed

Breslin Builders has recently completed the Kemp Retail Center on Cactus in southwest part of Las Vegas, Nevada.  The inline retail center includes a free standing restaurant drive-thru pad shell building also.  Other items included as part of the project include full half-street improvements on Cactus, a pump house for the required fire pump (due to low water pressure in the developing area), and full site improvements.

Photos of the completed work are below: