Tag Archives: construction

shareDOWNTOWN Apartments | August 2019 Progress

Grading is completed and underground plumbing and site utility work is progressing on the 63 unit mixed-use apartment project Breslin Builders is providing design-build services for.  The downtown located project at Casino Center and Colorado is on track for a 2nd quarter completion in 2020.

Progress photos are below:

shareDOWNTOWN Apartments | July 2019 Progress

Site work has begun on the new multi-story mixed used apartment project in downtown Las Vegas, Nevada.  The project will have two ground floor retail spaces, enclosed on grade parking, and 3-levels of apartments above the concrete podium consisting of 63 units total.  Each unit is designed as a studio apartment containing approximately 480 square feet each.  The project also has three community/gathering rooms.  Located at the southwest corner of Casino Center Boulevard and Colorado Avenue, the project is anticipated to be completed April/May 2020.  Breslin Builders provided design-build services for the project.

Progress photos are below:

Eastern Storage Center | July 2019 Progress

Breslin Builders has begun the site work for a new self-storage facility to be located at Eastern and Horizon Ridge in Henderson, Nevada.  The initial work includes deep over excavations of the existing soils in preparation for final grading and building pads.  The multi-level self-storage facility, along with the ample covered exterior RV and boat parking area, is anticipated to be completed in 2nd quarter 2020.

Progress photos are below:

Huntridge Retail | July 2019 Roof Framing Progress

Breslin Builders, working for Dapper Construction and Dapper Development, has progressed the new two tenant restaurant building out of the ground.  Roof framing has progressed over the course of July, allowing the building to take shape and show the unique curve design.

More roof framing progress photos are below:

Cactus Plaza Expansion | July 2019 Progress

Work on the retail expansion at Cactus Plaza is progressing and stucco work has been completed.  The work involves the expansion of the end cap space into an existing patio area to allow more space for a future tenant improvement.  In addition to the new walls and stucco work shown in the photos below, the existing sloped patio slab was removed and a new flat slab was provided, as well as additional insulation, reworking of some minor plumbing and electrical items, and eventually the installation of new storefront systems in the existing opening and removal of the existing south facing storefront to expand the interior area.

Breslin Builders provided the original construction for the center in 2015-2016 and are providing design-build services for this new expansion work.  The work is progressing and will be completed by the end of July 2019.

Progress photos are below:

Huntridge Retail | July 2019 Progress

Breslin Builders, working for Dapper Construction and Dapper Development, has progressed the new two tenant restaurant building out of the ground.  Roof framing has progressed starting in July, allowing the building to take shape and show the unique curve design.

Progress photos are below:

  

Cactus Plaza Expansion | June 2019 Progress

Work on the retail expansion at Cactus Plaza has started.  The work involves the expansion of the end cap space into an existing patio area to allow more space for a future tenant improvement.  In addition to the new walls and storefront, the existing sloped patio slab was removed and a new flat slab was provided, as well as additional insulation, reworking of some minor plumbing and electrical items, and eventually the installation of new storefront systems in the existing opening and removal of the existing south facing storefront to expand the interior area.  The existing stucco on some of the walls was also removed for the future tenant improvement work.

Breslin Builders provided the original construction for the center in 2015-2016 and are providing design-build services for this new expansion work.  The work is progressing and will be completed by the end of July 2019.

Progress photos are below:

Huntridge Retail | June 2019 Progress

Breslin Builders, working for Dapper Construction and Dapper Development, has progressed the new two tenant restaurant building out of the ground.  The slab has been poured and the unique CMU walls are being completed.

The building, designed by BunnyFish Studios, has a very unique and custom curvilinear roof, making this a one of a kind structure.  Housing two locally recognized restaurants, Roberto’s Taco Shop and Capriotti’s Sandwich Shop, the space will be a welcomed addition to the existing Huntridge Shopping Center at Charleston Boulevard and Maryland Parkway.

Progress photos are below:

Huntridge Retail | May 2019 Progress

Breslin Builders, working for Dapper Construction and Dapper Development, has progressed the new two tenant restaurant building out of the ground.  After a few months of existing utility relocation, site work, and underground installations, we have columns in place ready to put the slab.

The building, designed by BunnyFish Studios, has a very unique and custom curvilinear roof, making this a one of a kind structure.  Housing two locally recognized restaurants, Roberto’s Taco Shop and Capriotti’s Sandwich Shop, the space will be a welcomed addition to the existing Huntridge Shopping Center at Charleston Boulevard and Maryland Parkway.

Progress photos are below:

  

Craig and 95 Retail | August 2018 Progress

More progress on the Craig and 95 Retail shell building for Dapper Development.  Stucco is completed and primed, CMU planters being finished, decorative steel items have been installed, as well as other items progressing.

Progress photos are below:

Sobb Avenue Warehouse | June 2018 Progress

Breslin Builders has started the site work for the new 32,000 square footage multi-tenant Sobb Avenue Warehouse project.  Clearing and grubbing is taking place in anticipation of a final civil improvement permit.  Additionally, the site will have rock crushing and caliche removal started.  Progress photos are below: