shareDOWNTOWN at 11th | March 2022 Progress

All City of Las Vegas Building and Public Works permits are finalized and pulled for our new project being completed for Cherry Development! Underground plumbing work is progressing, as well as excavation for the footings. Site utilities are underway. A lot is starting to happen on this 84-unit, 4-story apartment project in downtown Las Vegas, Nevada, and soon things will start coming out of the ground.

shareDOWNTOWN Apartments | June 2020 Progress

Much progress has been made on the 63 unit apartment project Breslin Builders has provided design-build services on for Cherry Development.  The project is nearing completion with the site work progressing, unit finishes being installed, and inspections taking place.

 

 

 

 